# Collateralisation fee and asset under-delivery charge

> What a delivery shortfall costs you, and how it reaches your account.

Knowledge hub · Settlement & Invoices

3 min

What a delivery shortfall costs you, and how it reaches your account.

## In short

When your asset delivers less than it was committed to, the missing power still has to be covered towards the market. **EBX covers it at all times.** Your contract provides for that cover and sets its price.

* * *

## Who this is for

**Asset owners and commercial teams** reconciling a collateralisation fee or an asset under-delivery charge.

## Which shortfalls are charged

A shortfall is only charged when delivery is more than 5% below the requirement for more than 10 seconds, or more than 10% below it for more than 5 seconds. Smaller or shorter deviations stay inside the tolerance band and cost nothing.

Once a shortfall crosses that band, the whole missing power is charged, from its very first second.

## Types of shortfall

| Part of the shortfall | What you pay |
| --- | --- |
| Within your contractual collateral capacity | the **collateralisation fee**, charged for each started hour of cover at the rate set in your contract |
| Beyond your contractual collateral capacity | the same fee, **plus** the **asset under-delivery charge** on the energy beyond the collateral capacity |

Both apply together when a shortfall goes beyond your collateral capacity: the fee for the cover, and the charge on the part that exceeds it. Your contractual collateral capacity is typically sized to the asset’s largest technical unit.

## How are shortfalls priced?

EBX procures cover in blocks of one full hour. The first charged second of a shortfall buys a whole hour, regardless of its actual duration.

The cover is the size of the shortfall, rounded up to the next 0.2 MW. A four-minute shortfall therefore costs the same as a full-hour one.

-   If the shortfall grows while the hour is running, a new hour of cover is bought for the larger amount, and the unused part of the smaller cover is credited back to you.
-   If the shortfall is still there when the hour is over, the next hour starts.
-   The full hour is billed in the 15-minute settlement block in which it started.

### Worked example: a 4 MW shortfall for 20 minutes

A connected asset is asked for 10 MW but delivers only 6 MW for 20 minutes, from 10:00 to 10:20.

| Input | Value |
| --- | --- |
| Requested power | 10 MW |
| Delivered power | 6 MW |
| Shortfall | 4 MW |
| Duration | 20 minutes, 10:00 to 10:20 |
| Contractual collateral capacity | 3 MW |
| Collateralisation rate | €38 per MW per hour |
| CBMP in that direction | €120/MWh |

Step 1: Collateralisation fee.

Cover is procured for the full 4 MW shortfall, rounded up to the next 0.2 MW, for one started hour.

Collateralisation fee = 4 MW × 1 h × €38/MW/h = €152.00

Step 2: Asset under-delivery charge.

Only the part beyond the 3 MW contractual collateral capacity is charged.

Power beyond the collateral capacity = 4 MW − 3 MW = 1 MW

Under-delivered energy = 1 MW × ⅓ h = ⅓ MWh

Asset under-delivery charge = ⅓ MWh × €120/MWh = €40.00

| Charge | Amount |
| --- | --- |
| Collateralisation fee | €152.00 |
| Asset under-delivery charge | €40.00 |
| Total for the shortfall | €192.00 |

## How this reaches you

-   The **collateralisation fee** is invoiced together with your connectivity fee on the 5th of the month after delivery, and paid by you to EBX.
-   The **asset under-delivery charge** is issued with your market settlement towards the end of the month after delivery, and netted against it, so the payout you receive already accounts for it.