Knowledge hub · Settlement & Invoices

6 min

How delivery quality impacts your revenue

What happens to your potential revenues when an asset performs outside the agreed quality band.

In short

Your asset earns from the power it actually delivers and from the capacity its energy buffer can actually back. When delivery or the buffer leaves the agreed quality band for too long, the affected product stops earning for a defined period.

After that, your asset must prove it can deliver what is expected, and then earns again on that basis.


Who this is for

Asset owners, O&M teams and optimisers seeking to increase settlement revenue and ensure the asset performs as expected on the market.

The quality limits

What is assessedA quality break occurs when
FCR responsethe response deviates by more than 5% from the target for more than 10 seconds, or by more than 20% for more than one second
Energy buffer (aFRR and FCR capacity)the allocated buffer falls more than 5% below the required buffer for more than 10 seconds
aFRR deliverydelivery deviates by more than 5% from the expected target for more than 10 seconds, or by more than 10% for more than 5 seconds

The reference is the setpoint, or the permitted ramp while the asset is still moving towards it (an asset that follows its prequalified ramp does not break the limits even though it has not reached the setpoint yet). Deviations that stay inside the band are not a quality break.

At a 10 MW setpoint the permissible band is 9.5 to 10.5 MW. A dip to 9.8 MW is fine. Delivery outside 9.0 to 11.0 MW for more than 5 seconds is not.

What happens after a quality break

Two clocks start at the moment of a quality break.

another break restarts the 20 minutesNormal deliveryfull revenue20-minute pauseno revenueProven levelrevenue up to itFull revenueif at least 95% provenqualitybreakpauseendsprovesat least 95%
The lifecycle of a quality break: normal delivery earns in full until a break, which starts a 20-minute pause with no revenue. A further break during the pause restarts the 20 minutes. When the pause ends, the asset earns up to the level it has proven over 60 continuous seconds, and returns to full revenue once it proves at least 95% of the setpoint it was on when the break happened.

The 20-minute pause decides when you can earn again.

From the break onwards, the affected product earns nothing for at least 20 minutes. If another quality break happens while the pause is running, the 20-minute block starts again from that point.

The 60-second proof decides how much you can earn.

During and after the pause, EBX looks for the highest power level the asset held for 60 continuous seconds. For every second of that minute, EBX validates the lower value of what was delivered and what was requested. The highest sustained value is the proven level.

The three stages

StageWhat the asset earns
During the 20-minute pausenothing, even if the asset has already recovered
After the pause, with a proven level below the original setpointthe energy delivered up to the proven level. Every higher level held for 60 continuous seconds raises it
After the pause, once it has proven at least 95% of the setpoint it was on when the break happenedfull delivery again

If nothing has been proven by the time the pause ends, there is still no revenue. Earning starts with the first proof.

Worked example: a 10 MW setpoint

A connected asset on a 10 MW aFRR setpoint leaves the quality band at 10:00.

TimeWhat happensWhat the asset earns
10:00Delivery leaves the quality band and a quality break is recorded. The setpoint at that moment, 10 MW, becomes the recovery target.€0
10:00 to 10:20The 20-minute pause runs. The asset holds 6 MW for 60 continuous seconds, so 6 MW is proven.€0
From 10:20The pause is over. The asset earns for the energy it delivers, up to the proven level.up to 6 MW
Once it holds at least 9.5 MW for 60 continuous seconds95% of the original 10 MW is proven and normal delivery returns.up to 10 MW

Nothing is earned during the 20-minute pause, and until the asset proves 9.5 MW the remaining 4 MW of the original 10 MW is revenue it could have earned and did not.

Reserved capacity

Capacity is not paid for power delivered, but for power kept available. What is assessed is therefore the energy buffer the asset keeps allocated to the product.

ProductRequired energy buffer
aFRR capacity1 MWh per accepted MW, in the direction of the award
FCR⅓ MWh per accepted MW, in each direction

When an asset holds both products, the FCR requirement is allocated first, because FCR has the highest delivery priority. aFRR capacity is backed by the energy that remains.

An asset with 5 MW of aFRR+ capacity and 3 MW of FCR needs 5 MWh in the positive direction for the aFRR capacity, and 1 MWh in each direction for FCR. That is 6 MWh positive and 1 MWh negative in total. The +1 MWh and −1 MWh are allocated to FCR first, and the remaining 5 MWh positive back the aFRR capacity.

What a buffer quality break does

The sequence is the same as for delivery: 20 minutes without payment, then payment limited to what the asset proves.

  • A buffer level counts only if it is held for 60 continuous seconds, and the lowest observation inside that minute sets the level.
  • 1 MWh of allocated buffer proves 1 MW of aFRR capacity in that direction. ⅓ MWh in each direction proves 1 MW of FCR, and both directions have to hold within the same 60 seconds, so the weaker direction decides.
  • Payment never exceeds the capacity you were awarded, even if the buffer would support more.
  • Full payment returns only once the entire original required buffer is held for 60 continuous seconds. The 5% tolerance that decides whether there was a break does not reduce this.

Worked example: 5 MW of accepted aFRR capacity

An asset holds 5 MW of accepted aFRR capacity and its buffer breaks at 10:00.

StepValue
Accepted capacity5 MW
Required buffer5 MWh in that direction
Buffer quality break at10:00
Highest buffer held for 60 continuous seconds afterwards3 MWh
Proven capacity3 MW
Revenue 10:00 to 10:20€0

Capacity revenue after the pause = 3 MW × €20/MW = €60.00

At an illustrative €20/MW, the asset earns €60.00 after 10:20 instead of the €100.00 that 5 MW would have earned. Full payment returns once all 5 MWh are held for 60 continuous seconds.

Worked example: why FCR needs both directions at once

An asset holds 3 MW of FCR, so it needs 1 MWh positive and 1 MWh negative. During one 60-second window the positive buffer never drops below 0.9 MWh and the negative never below 0.6 MWh.

  • the positive buffer at 0.9 MWh supports 2.7 MW;
  • the negative buffer at 0.6 MWh supports 1.8 MW.

Proven FCR capacity = min(2.7 MW, 1.8 MW) = 1.8 MW

Capacity revenue after the pause = 1.8 MW × €15/MW = €27.00

The weaker direction decides, so that window proves 1.8 MW. At an illustrative €15/MW the asset is paid €27.00 instead of €45.00 for the full 3 MW. Holding 1 MWh positive in one minute and 1 MWh negative in the next does not help: both directions have to hold together, within the same 60 seconds.

FCR delivered energy is not compensated, but the FCR response is still assessed. A response quality break pauses FCR capacity revenue for 20 minutes in exactly the same way.

Shortfall charges may also apply

Whatever the asset does not deliver still has to be covered towards the market, and EBX covers it at all times.

That cover is charged as the collateralisation fee, and anything beyond your contractual collateral capacity also carries the asset under-delivery charge. Both are separate from your market revenue. Collateralisation fee and asset under-delivery charge explains how each is calculated.