EBXSign inBook a demo

Knowledge hub · Settlement & Invoices

3 min

Collateralisation fee and asset under-delivery charge

What a delivery shortfall costs you, and how it reaches your account.

In short

When your asset delivers less than it was committed to, the missing power still has to be covered towards the market. EBX covers it at all times. Your contract provides for that cover and sets its price.


Who this is for

Asset owners and commercial teams reconciling a collateralisation fee or an asset under-delivery charge.

Which shortfalls are charged

A shortfall is only charged when delivery is more than 5% below the requirement for more than 10 seconds, or more than 10% below it for more than 5 seconds. Smaller or shorter deviations stay inside the tolerance band and cost nothing.

Once a shortfall crosses that band, the whole missing power is charged, from its very first second.

Types of shortfall

Part of the shortfallWhat you pay
Within your contractual collateral capacitythe collateralisation fee, charged for each started hour of cover at the rate set in your contract
Beyond your contractual collateral capacitythe same fee, plus the asset under-delivery charge on the energy beyond the collateral capacity

Both apply together when a shortfall goes beyond your collateral capacity: the fee for the cover, and the charge on the part that exceeds it. Your contractual collateral capacity is typically sized to the asset’s largest technical unit.

How are shortfalls priced?

EBX procures cover in blocks of one full hour. The first charged second of a shortfall buys a whole hour, regardless of its actual duration.

The cover is the size of the shortfall, rounded up to the next 0.2 MW. A four-minute shortfall therefore costs the same as a full-hour one.

  • If the shortfall grows while the hour is running, a new hour of cover is bought for the larger amount, and the unused part of the smaller cover is credited back to you.
  • If the shortfall is still there when the hour is over, the next hour starts.
  • The full hour is billed in the 15-minute settlement block in which it started.

Worked example: a 4 MW shortfall for 20 minutes

A connected asset is asked for 10 MW but delivers only 6 MW for 20 minutes, from 10:00 to 10:20.

InputValue
Requested power10 MW
Delivered power6 MW
Shortfall4 MW
Duration20 minutes, 10:00 to 10:20
Contractual collateral capacity3 MW
Collateralisation rate€38 per MW per hour
CBMP in that direction€120/MWh

Step 1: Collateralisation fee.

Cover is procured for the full 4 MW shortfall, rounded up to the next 0.2 MW, for one started hour.

Collateralisation fee = 4 MW × 1 h × €38/MW/h = €152.00

Step 2: Asset under-delivery charge.

Only the part beyond the 3 MW contractual collateral capacity is charged.

Power beyond the collateral capacity = 4 MW − 3 MW = 1 MW

Under-delivered energy = 1 MW × ⅓ h = ⅓ MWh

Asset under-delivery charge = ⅓ MWh × €120/MWh = €40.00

ChargeAmount
Collateralisation fee€152.00
Asset under-delivery charge€40.00
Total for the shortfall€192.00

How this reaches you

  • The collateralisation fee is invoiced together with your connectivity fee on the 5th of the month after delivery, and paid by you to EBX.
  • The asset under-delivery charge is issued with your market settlement towards the end of the month after delivery, and netted against it, so the payout you receive already accounts for it.

Send feedback

This goes straight to the docs team on Slack, with the page you are on. It is not attributed to you, so say who you are if you would like an answer.

0/2000